Order of works when renovating a flat: 12 steps from plan to keys

HR EN

Flat owner and electrician planning the order of works over a floor plan

Gigron

You have bought an older flat, or you are finally starting a renovation. The tradespeople are booked and the tiles are chosen. Then the question: who comes first? The order of works when renovating a flat decides how much you pay and how long you wait. It also decides whether finished work has to be opened up again. The rule is simple: first what goes inside walls and floors, then what goes on the walls, and last what can be moved.

Bathroom under renovation: new pipes in the wall and a waterproofed shower area

This guide gives you 12 steps from plan to handover, what can run in parallel, the most common mistakes and answers to questions like "painting or parquet first". The order is put together from the guidance of several Croatian contractors and technical instructions for screed. Agree the final plan for your flat with your contractor, because it depends on what you are changing.

Order of works at a glance

Step What is done Why at that point
1. Plan and paperwork layout, sockets, materials, permits everything later depends on these decisions
2. Protection and demolition strip-out, demolition, rubble removal work starts on a bare space
3. Walls and drywall framing new walls, openings, metal studs installers need to know where walls are
4. First-fix installations water, drainage, electrics, heating, data they go into walls and floors before closing
5. Windows new windows reveals are finished together with the walls
6. Plastering and closing up plaster, chases, drywall boards, suspended ceiling the base for all finishes
7. Screed new floor base, underfloor heating the longest wait, drying
8. Waterproofing and tiles bathroom, kitchen, hallway wet and dirty work
9. Skim coating and painting ceiling, then walls before floors, so the floor stays clean
10. Floors parquet, laminate, vinyl once screed is dry and wet work is done
11. Doors and second fix doors, sockets, sanitaryware, lights, kitchen on finished surfaces
12. Cleaning and handover inspection, snag list before you move in

Three rules help when you are not sure what comes first:

Need someone for this job? Describe it and get quotes →

1. Plan, materials and paperwork

A renovation starts on paper, not with a hammer. Before the first blow, decide where the kitchen, washing machine, TV and air conditioner go. Decide whether you want a bath or a shower and where you need sockets and lights. Each of those decisions sets where pipes and cables run. One contractor puts it this way: a socket you remember after the screed is poured means breaking a finished floor and waiting for drying again.

At this step, also order materials with longer delivery times: tiles, sanitaryware, interior doors, parquet and a made-to-measure kitchen. One contractor's calculator assumes about seven weeks for a kitchen from order and about four weeks for interior doors. That is their estimate, not a rule, but it shows why you should not order at the last minute.

Check the paperwork too:

This is a summary, not legal advice. If in doubt, ask a licensed designer.

2. Protection and demolition

Before demolition, protect everything that stays: windows, radiators, the front door and floors that are not being replaced. Contractors recommend protecting the stairwell and lift as well. Floors are covered with cardboard or sheeting. Rooms that are not being touched are sealed off with plastic sheeting, ideally with a zip door.

Then comes the strip-out: old tiles, sanitaryware, floors, worn-out screed, old installations and walls that are being removed. A full renovation creates a lot of rubble, so a skip is usually ordered. If it will stand on the street or a public car park, check whether you need approval to use public space. You can find removal companies under construction waste removal.

3. Walls and drywall framing

After demolition, new walls are built and larger damage is repaired. Metal studs go up for drywall walls and suspended ceilings. One contractor recommends boarding a drywall wall on one side only at first. The other side stays open until installations are run through it. Moisture-resistant boards are used in bathrooms and kitchens. Costs are in the guide drywall cost per m².

4. First-fix installations: water, drainage, electrics, heating

You see this work least afterwards, and it costs most if it goes wrong. The usual order:

  1. Water and drainage. New runs for the bathroom, kitchen and washing machine. Drains need a constant fall towards the building's stack.
  2. Electrics. Chases in the walls, conduit, cables, back boxes for sockets and switches, and a new consumer unit if needed.
  3. Heating and cooling. Radiator pipework or underfloor heating and pre-installation for an air conditioner.
  4. Low voltage. Internet, TV and intercom.

Water and drainage go first because pipes are rigid and drains need a fall. Cables go around pipes, not the other way round. Before the chases are closed, the water supply is pressure-tested. Photograph all installations with a tape measure held against the wall. That way you will know where it is safe to drill even ten years later.

In an older flat, check old installations even if they still work. If you plan an induction hob, air conditioning or a new kitchen layout, the old wiring may not be enough. While walls are open, replacing it is easiest. You can find tradespeople under electrical installation and plumbing work.

5. Windows and balcony doors

If you are replacing windows, do it before plastering and skim coating. Installation damages the reveals, and this way they are repaired together with the other walls. If windows are changed at the end, the reveals get done twice. Indicative prices are in the guide PVC windows cost with installation.

6. Plastering, closing chases and drywall boards

Now the installation chases are closed and new and damaged walls are plastered. Drywall walls and ceilings are boarded. Corner beads go on external corners so edges stay straight. If you are adding a suspended ceiling, cables for downlights must be inside it before it is closed.

7. Screed: the longest wait

When all installations in the floor are finished, the new screed is poured. Flats usually get a floating screed. Sound insulation goes underneath and an edge strip along the walls, so footsteps are not heard by the neighbours below.

This is where you wait the longest. For classic cement screed, a common rule of thumb is about one week of drying per centimetre of thickness, up to roughly 4 cm. Thicker layers dry more slowly. Cement screed manufacturers ask for at least 28 days before floor coverings, plus a moisture check. Before parquet or laminate, moisture is measured with the CM method, not by hand. A common limit for cement screed is 2.0 %, and 1.8 % with underfloor heating. Fast-drying screed can be covered sooner, according to the manufacturer's instructions. More in the guide screed drying time, and costs in floor screed cost per m².

In the first days, do not dry screed with heaters or draughts, because drying too fast can make it crack.

What to do while the screed dries

The drying time does not have to be lost. While the screed is not ready for parquet, you can do:

8. Waterproofing and tiles

In the bathroom, waterproofing goes on before the tiles. One Zagreb contractor applies it to the whole floor, turned up the walls, and on the walls of the shower area to a height of at least 2 m. It goes on in two coats, with sealing tape in corners and around the drain. The fall towards the drain is formed in the base before waterproofing, not with a thicker layer of tile adhesive. Prices are in the guides waterproofing cost per m² and bathroom renovation cost.

Tiling is wet and dirty work. So in the bathroom, kitchen and hallway it comes before the final painting and parquet. Corners and the joint between wall and floor are not filled with grout but with silicone. Tiling costs are in the guide tiling cost per m².

9. Skim coating and painting

Skim coating is usually done in two coats, with sanding. Then come a primer and two coats of paint. Always work from the ceiling down to the walls. Radiators are taken off the walls being worked on and put back after painting. Otherwise an unfinished patch of wall stays behind them. Why primer matters is in the guide wall primer before painting, and prices in wall painting and skim coating cost per m².

Some contractors leave the final coat of paint for the very end, after floors and doors. Small marks from fitting are then touched up, with the floor well protected.

10. Floors: parquet, laminate or vinyl

Parquet or laminate is laid when the screed is dry and there is no more wet or dusty work in the flat. That way the new floor is spared paint drips, sanding dust and ladders. Solid parquet that is glued, sanded and varnished on site needs a few more days of drying. Plan for it. Prices per square metre are in the guides parquet installation and laminate installation.

11. Doors, second fix and kitchen

Interior doors are fitted after the floors. The frame is set on the finished floor, and the floor thickness determines the gap under the door leaf. So the answer to "doors or laminate first" is almost always: the floor first. Sizes are in the guide interior door dimensions, and prices in interior doors cost with installation.

Then comes the second fix: sockets, switches, lights, sanitaryware, taps, radiators and skirting. A made-to-measure kitchen gets its final measurement only when the walls are level and the floor is laid. Every centimetre of plaster or tiles changes the size. If you set water and socket positions in step one, fitting goes without changes.

12. Cleaning and handover

At the end the protection comes off and the flat is cleaned thoroughly. There are also specialists for post-construction cleaning. At handover, walk through every room with the contractor. Open every tap, switch on every light, open every door and window. Write every small issue on a list and agree a deadline for fixing it. What you can ask for if something fails later is in the guide warranty on building work.

When you renovate only part of the flat

Not changing everything? The order stays the same; you just skip the steps you do not need.

How long does a flat renovation take

It depends on the size of the flat, the scope of work and the type of screed. Two examples from practice:

These are contractors' estimates, not a promise. Waiting for drying and deliveries cannot be sped up by adding people. That is why ordering materials early saves the most time.

One contractor does not recommend living in the flat during a full renovation. For part of the time there is no water or electricity, and demolition and chasing create a lot of noise and dust.

The most common mistakes in the order of works

  1. Materials are ordered at the last minute. Tradespeople wait for tiles or doors, and everything slips.
  2. Parquet or laminate goes on damp screed. The floor can later lift, open up or creak.
  3. Socket layout changes after skim coating. A finished wall is chased, then skimmed and painted again.
  4. Windows are replaced at the end. The reveals get done twice.
  5. The kitchen is measured before plaster and tiles. Units do not fit, or gaps stay along the wall.
  6. Old installations stay because they still work. A fault after the renovation means opening new walls and tiles.
  7. Installations are closed without a test and photos. Later nobody knows where the pipes are.

Who keeps track of the order

If you hire the plumber, electrician, tiler and painter yourself, you are the coordinator. You book dates, check that the previous stage is finished and sort out who is responsible when something goes wrong. One contractor estimates that with separate trades there is about a week of waiting at each handover between stages. With one contractor running all stages, that responsibility is theirs.

If you go with separate tradespeople, make a table: step, tradesperson, start date, end date and what must be finished before it. Send it to everyone. For a full renovation you can also look for contractors under flat renovation, for example in Zagreb, Split or Osijek. What a full renovation costs per square metre is in the guide apartment renovation cost per m².

Example request to a tradesperson

This is a made-up example:

"I am renovating a 55 m² flat on the 3rd floor of a building with a lift. I am replacing the wiring, the bathroom and the floors. The windows are being replaced in the first week. I am looking for a contractor for screed and tiles after the electrician finishes, in about three weeks. Please send a price and how many days you need."

How to write a good request is in the guide how to write a request to a tradesperson.

Find tradespeople through Gigron

On Gigron you post a job for free and tradespeople reply with offers. You can post the whole renovation or job by job, in exactly the order you need. Download the app:

FAQ

What comes first when renovating a flat?

The plan. First decide the layout of the kitchen, bathroom, sockets and lights, and order materials with longer delivery times. The first physical job is protecting the space and demolition.

Painting or parquet first?

Painting first. Skim coating and painting go before parquet and laminate, so the floor is not damaged by paint, dust and ladders. Some contractors leave the final coat of paint for the end, with the floor well protected.

Doors or laminate first?

Laminate or parquet first. The door frame is set on the finished floor, and the floor thickness determines the gap under the door leaf.

Tiles or painting first?

Tiles first. Tiling is wet and dusty work, so it comes before the final painting of the walls.

How long should I wait to lay parquet after screed?

For cement screed, a common rule of thumb is about one week per centimetre, up to about 4 cm thick. Manufacturers ask for at least 28 days and a moisture check. Before laying, moisture is measured with the CM method.

Do I need a permit to renovate a flat?

For work that does not touch walls or the load-bearing structure, such as tiles, painting and floors, a permit is usually not needed. Alterations to partition walls and openings in load-bearing walls need a main design, and larger works need a building permit. In a block of flats, contact the building manager before work starts.

Summary

The order of works when renovating a flat: plan and materials, protection and demolition, walls, installations, windows, plastering, screed, waterproofing and tiles, skim coating and painting, floors, doors and second fix, then cleaning and handover. First what goes inside walls and floors, then what goes on the walls, and last what can be moved. Order materials early, photograph installations before closing them and never lay a floor on damp screed.